Motorway E75 (subsection Caričina Dolina –Manajle tunnel) in the Republic of Serbia: Visit to the construction site and Prime Minister’s compliments

Oct 17, 2016

The Prime Minister of the Republic of Serbia Aleksandar Vučić with his collaborators visited the site of construction of motorway E75, section Caričina Dolina – Vladičin Han on the southern branch of Corridor 10 on October 16, 2016. He was satisfied with executed works on the section and he especially complimented the company “Integral Inženjering” plc. Laktaši.

He emphasized that it is the most complex and most demanding section in length of 6.7 km, which also includes the construction of Manajle tunnel in length of 1.800 m, as well as 12 other tunnels.

He mentioned that the most beautiful slopes were performed on that part of motorway and that the PE “Koridori Srbije” and Ministry of Transportation, Construction and Infrastructure completed very successful job.

According to the abovementioned, the Prime Minister expressed a special thanks to company “Integral Inženjering” plc. Laktaši from the Republic of Srpska, which worked under very difficult conditions without any problems, and he congratulated workers on successfully executed works.

The finishing of t section will be very important because it will enable opening of new factories and plants, but also it will be important for tourism development. It will make the Vlаsina lake, Vrаnjska and Buјаnоvаčka spa resorts and many other places on south of Serbia closer to tourists, said Vučić.

We remind you that company “Integral Inženjering“ plc. Laktaši executes the works on subsection Caričina Dolina – Manajle tunnel in length of 6.7 km. This subsection is the most demanding for execution on the section of Corridor 10 in Serbia.

In this phase, the works on designed structures and the works along the whole motorway alignment are executed at the same time.

The rehabilitation and protection of slopes with geotechnical stabilization system and construction of retaining walls with embankments and cut are intensively executed in the area in front of bridges Morava 1 and Morava 2, as well as in the area of these bridges.

The “Momin kamen” viaduct, which is the largest structure on this section, is in the final phase of construction, after the works on left structure are completed and the finishing of works on the right structure are planned to be executed until the end of month.

The works on piling are continued at several locations on the alignment.

More about visiting: http://www.srbija.gov.rs/vesti/vest.php?id=276236