The works on construction of the motorway section Rača – Bijeljina, of the total length l=21 km has started on September 15, 2022 and at the beginning the project progressed by the planned schedule. In time, the works have slowed down due to reasons not...
During the night of October 24–25, 2025, the final breakthrough of the tunnel was achieved between the excavation points 6 and 1, at chainage 0+508.5. This event, which is of great engineering importance, marked the completion of underground excavation works for the...
Integral inženjering a.d. Laktaši on September 16, 2025 successfully completed construction works on the expressway Okučani – border of Bosnia and Herzegovina on the section: interchange “Novi Varoš” – bridge on the Sava (phase 2). We remind...
Integral inženjering, which is carrying out works on the construction of the motorway on Corridor 5c, section: Rudanka bridge – Putnikovo brdo 2 tunnel (Doboj bypass), hosted on May 12, 2025 representatives of the Construction School from Banjaluka and JP...
On 9, April 2025, Minister of Transport and Communications of the Republic of Srpska Mr. Nedeljko Čubrilović and Acting Director of the Public Company “Autoputevi Republike Srpske” d.o.o. Banja Luka Mr. Nedeljko Ćorić, with associates and representatives...
Doboj Bypass, of length of 5.5 km, represents the most complex section for execution of works, in the sense of engineering, due to very demanding terrain and poor geological conditions. This resulted in about 45% of its length being in structures. In this phase, the...