The final blasting operation in the headrace tunnel of the future Dabar Hydropower Plant has beensuccessfully completed

Oct 28, 2026

A major milestone for Integral! We have completed the final concrete lining section of the headrace tunnel for the future Dabar Hydropower Plant. At 12,125 metres, it is the longest tunnel of its kind in the Western Balkans and the second longest in South-East Europe. The tunnel will carry water from the Nevesinje reservoir to the powerhouse in Dabarsko polje, as the key structure of the Upper Horizons of the Trebišnjica project. With 160 MW of installed capacity, HPP Dabar will generate around 500 GWh of clean energy a year. Thank you to every member of our team whose expertise and perseverance, day after day underground, made this possible.